This form is for current Anoka Municipal Utility (AMU) customers only.
Please make sure you have sufficient time for completion as this form will not save progress for use at a later time.
Upon submission, it will be e-mailed to the utility shop office personnel, including the master electrician.
Please call 763-576-2903 with any questions.
For Option (B) Step 1.
Page 95 of the Distributed Generation Policy
2.) Send $300 pre-application fee payable to AMU and to the address of:Anoka Municipal UtilityAttn: Admin - Solar Fees501 Pierce StreetAnoka, MN 55303
3.) Wait for approval. The Utility will provide the applicant with a Pre-Application Report within 15 business days once the completed Pre-Application Report Request and a $300 fee is submitted to the Utility.
4.) Complete and submit the Interconnection Application (PDF).
After information from steps 1 through 4 above are received, the review process will start at AMU, and installation may begin.